home » our
work » case studies » Sid
Peterson Memorial Hospital
Case Study:
Sid Peterson Memorial Hospital, Kerrville,
TX
New Flooring Construction Experts
Beginning in 1998, Kerrville-based Sid Peterson Memorial Hospital
began a major expansion to add a 52,000 square-foot ambulatory care
center to its complex.
Over the next two years, the state-of-the-art Peterson Regional
Ambulatory Care Center was constructed on 35 acres. The facility
houses all hospital outpatient services including day surgery, imaging
and a rehabilitation center featuring an exercise gym and spacious
indoor therapy pool.
Known for its quality installation and service, Intertech Flooring
was selected to install flooring in the hospital's pool treatment
area, where temperatures average 90 degrees and RH is approximately
85 percent. "Working with a qualified flooring contractor
is critical on complex jobs like this," says hospital administrator
Mike Williams. The architect's original specified product was
a 12" x 12" solid vinyl tile installed with a solvent free
two-part epoxy adhesive - the type of product with which Intertech
has extensive experience. Intertech completed the installation in
April 2000.
Problem-Solving Attention
Soon, however, Williams would learn how important it is to work
with a flooring contractor that not only is qualified, but that also
stands behind their work. About 18 months after construction,
Williams began noticing rust and chalk around the seams of the tiles. He
called in the general contractor, flooring manufacturer and Intertech
to assess the problem.
"The moisture tests performed prior to the original installation
showed that the concrete's moisture level was within the manufacturer's
tolerances. But, it was clear that moisture somehow was effecting
the bond of the material installed," recalls Bill Imhoff, Intertech
Flooring CEO. "We needed to determine where the moisture
was coming from and how to overcome it.
"We were already six months past our warranty when the problem
first appeared. Other companies might have walked away form
the situation, but that's not the way we do business. We believe
in standing behind our work and following it through."
Rather than opt for a quick fix that might not be a long-term
solution, Intertech and general contractor Faulkner Construction
began an exhaustive investigation, spending countless hours and
dollars trying to identify why the tiles weren't adhering. They
brought in experts, took samples and ran lab tests, all in an effort
to determine if the problem was faulty installation, a failure
of the adhesive, a product that couldn't withstand high moisture
environments, or something else.
Imhoff and Intertech Flooring Project Manager Scott Richter also
called in the manufacturer to perform tests, but they never heard
the results. “We felt we owed the manufacturer of the product
the chance to be part of the solution,” says Imhoff. “But
we didn’t get the support we needed. In the end, we had to
take care of it ourselves.”
Testing was complicated by the fact that the hospital was used
daily for rehabilitation services. "Our pool is a source of
revenue, so we simply couldn't close it for weeks for testing. Even
though it meant more hassle for them, Intertech went to great lengths
to conduct the testing without necessitating closing the pool," says
Williams.
Expert Advice
Ultimately, after 11 months of testing everything from the pool
water to environmental moisture levels to the adhesive itself - and
with still no lab results from the manufacturer - Intertech decided
it was time to look for a different flooring product. "We had
followed the process recommended by the manufacturer, and determined
that moisture was not coming through the slab and that the adhesive
was breaking down due to the pool water," says Imhoff. "At
that point we knew we needed to change products and our approach
to dealing with the moisture."
Architectural firm The Bower Downing Partnership Inc. proposed
five possible replacement products, and the hospital turned to
Intertech for their advice. "One of the possible product replacements
was slip resistant which we needed for safety, but I didn't feel
was durable enough. Another product we looked at was a loose lay,
which wasn't a bad option because it would allow moisture to escape. But
I felt the best option was a sheet vinyl that can be heat welded
and is self-coving, ensuring 100 percent moisture protection," says
Imhoff. "In addition, the manufacturer was one with whom
we've worked extensively and who shares our customer service business
philosophy."
Resolving the Problem
To prepare the foundation for installing the product - Altro's
Marine 20/ Impressionist II - Intertech spared no expense. They
super-prepped the foundation by jack hammering the concrete down
to the bare slab, then sanding any remaining fine particles to
expose a clean, bare concrete surface. The Intertech team then
applied a moisture barrier to seal off moisture that had soaked
into the slab topically.
"Due to the tight time schedule, we didn't have the luxury
of letting the concrete dry out naturally," says Imhoff. "In
addition, we wanted to be sure we eliminated any residual contaminants
due to the excessive amount of water that had been trapped by the
floor."
To avoid pool downtime - and thus lost revenue for the hospital
- the Intertech installation team completed the installation in three
weeks over the Christmas season, taking only Christmas and New Year's
Day off.
"They had a tight schedule, and they met their deadline. To
lead the job, they brought in their best installers with extensive
experience in highly technical installations to make sure everything
was done 100 percent correctly. They devoted more people and
more supervision than they normally would have on a job, and really
went above and beyond expectations," recalls Williams.
The effort paid off. The new flooring has proven an ideal
choice for the pool area. Water penetration is no longer an
issue and the absence of seams makes cleaning easier. "Intertech's
recommendation for the Altro product was right on target. It
not only is ideal for the environmental demands of the room, but
it looks better than the original tile and patients like it because
it is easier on their feet," Williams says.
Lessons Learned
Bottom line, Williams says he now knows more than ever the importance
of dealing with reliable, knowledgeable contractors who know their
business and stand behind their work. "Unfortunately for
Intertech, their company took the entire financial hit for a product
problem, which speaks volumes about their business ethics," Williams
says. "They did what they said they'd do, and finished
when they said they would. I'll be a supporter of Intertech
for a long time to come."
|